Activity |
Date |
|
|
|
Concept Approval by State Board of
Education |
February-07 |
|
|
|
Referendum Approved |
March-07 |
|
|
|
Site Construction Documents
Complete/Final Review |
August-07 |
|
|
|
Site Design & Funding Approved by State
Board of Education |
September-07 |
|
|
|
Site Project out to Bid |
September-07 |
|
|
|
Site Bid Opening |
October-07 |
|
|
|
Site Funding Approval by the Commissioner
of Education |
October-07 |
|
|
|
Site Construction Initiation Date |
December-07 |
|

Pictures of the bi-weekly progress
meetings held on-site.
|
|
|
Building Construction Documents
Complete/Final Review |
January-08 |
|
|
|
Building Design & Funding Approval by
State Board of Education |
January-08 |
|
|
|
Building Project: Out to Bid |
February-08 |
|
|
|
Building Project: Bid Opening |
March-08 |
|
|
|
Final Funding Approval by Commissioner of
Education |
March-08 |
|
|
|
Building Construction Initiation Date |
April-08 |
|
|
|
Bond Date |
May-08 |
|
|
|
Substantial Completion Building & Site
|
May-10 |
|
|
|
Occupancy |
June-10 |